Club Capital Development Plans 2008-2010
Project 1 Floodlighting of All Weather Pitch,
Estimated Cost: €100,000-€115,000
Comment: Priority project Time Line: Completion Late -2008.
Funds Currently Available for Project from Club.
Project 2 Hurling Alley
Estimated Cost: €80,000 -90,000
Comment: Work to start on this in 2008.Certain Section of Funds Available.
Project 3 Sprinkler System for All Weather Pitch
Estimated Cost: €15,000( €25,000 for Automated system)
Comment: Planned for 2009.Funds needs to
be raised to cover costs.
Project 4 Club GYM
Estimated Cost: € Un Known
Comment: To be Decided
October 17th 2007
Clyda Rovers Development Committee:
Noel Walsh, John Dorgan, Aisling Murphy, John Roche, Fergal Cronin, Mick Dorgan, Padraig O'Mullane, Donie Mulchay, Cormac O'Sullivan